Overview

As demand for data centers accelerates, developers, investors and lenders are navigating an increasingly interconnected landscape of power availability, financing requirements and development risks. Bringing projects online requires more than access to energy or capital: it demands a coordinated approach to execution, risk allocation and long-term bankability.

At TMT Finance USA 2026, Carl Fleming of McDermott Will & Schulte convened and led the Data Center Leaders Exchange in New York, bringing together perspectives on speed to power, capital and M&A, and special situations. In summarizing the roundtable discussions, Fleming emphasized that the commercial value of a data center project increasingly depends on how its power, compute, development and capital requirements work together.

“One thing I’m hearing across all three tables is that power, capital and distress are not really separate conversations. The same risk that determines whether a project gets built also determines how it is financed — and ultimately what happens if it does not perform as planned.” — Carl Fleming, Exchange convenor and moderator

Five themes emerged from the discussions and Fleming’s closing synthesis.

Five takeaways

1. Think beyond speed to power — Focus on bankability

Securing power is necessary, but it is not sufficient. Developers must show that power can be delivered on a credible schedule and supported by workable interconnection arrangements, permits, equipment procurement, operating assumptions and contractual risk allocation. Lenders and investors are asking not only when power will be available, but whether the resulting project can be financed, built and operated on those terms. The relevant measure is speed to bankable power.

2. Underwrite the data center, compute, and power infrastructure together

Data centers, compute commitments and energy infrastructure cannot always be evaluated as independent assets. Power delivery dates affect construction and occupancy; customer and compute obligations affect revenue certainty; and both influence financing terms. Coordinated diligence across site control, interconnection, power procurement, equipment, customer contracts and capital structure can expose gaps that siloed underwriting misses. Increasingly, value — and risk — is allocated at the intersection of these elements.

3. Distinguish execution challenges from financial distress

Higher costs, permitting delays and power constraints do not automatically mean a project is distressed. Strong underlying demand can provide flexibility to renegotiate timelines, redesign projects or source alternative capital. But the distinction matters: unresolved delivery risk can become liquidity or refinancing risk, particularly when financing, equipment and customer milestones are misaligned. Investors should identify the point at which a solvable development issue becomes a capital-structure problem.

4. Look beyond traditional distress for M&A and investment opportunities

Special-situations opportunities may arise before formal distress. Projects with attractive sites, interconnection positions or customer demand may need a different sponsor, new development capital, revised commercial arrangements or a strategic partner to reach completion. That can create opportunities for acquisitions, joint ventures, recapitalizations and structured investments. The key is to distinguish assets with durable underlying economics from those whose risks cannot be reallocated at a financeable price.

5. Track policy and market signals that change the cost of capital

Grid access, interconnection rules, permitting, reliability requirements and cost allocation can determine which projects proceed — and who ultimately pays for supporting infrastructure. Changes in these rules can shift project economics as meaningfully as a movement in financing spreads. Investors and developers should evaluate regulatory and commercial risks together, rather than treating policy as a separate diligence workstream.

Looking ahead

Fleming closed the Exchange with a second observation:

“That brings us back to the question we started with. These transactions no longer fit neatly into the power, real estate, technology or capital boxes. The value is increasingly being created — and the risk increasingly being allocated — at the intersection.” — Carl Fleming, Exchange convenor and moderator

The next phase of digital infrastructure investment will be defined less by demand alone than by execution: which projects can secure deliverable power, align compute and customer commitments, allocate risk and attract capital on sustainable terms. These are connected development, financing and investment decisions — not separate conversations.

McDermott’s Powered Digital Infrastructure & Strategic Capital work brings together capabilities across AI, data center development, power and interconnection, project and structured finance, strategic investment, M&A, and exit. We help clients navigate the full lifecycle where AI, power, infrastructure, and capital converge.

To discuss these issues or a specific project, please contact Carl Fleming and the McDermott team.